cancel
Showing results for 
Search instead for 
Did you mean: 

Normal duration maintained at activity is not showing correct in graphical

Former Member
0 Kudos

Hi all,

Normal duration maintained at activity is not showing correct in graphical detail of network. for example if normal duration

4 days is maintain agaist any activity of network but when i go to graphical detail (Crtl+F9) then it shows 0 value.

any one has faced this error/situation........any idea/advice.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

I think you are referring to Tcode CN22 and Ctrl+F8.

After control+F8 click F7 and select lrg. or expanded

former_member299514
Participant
0 Kudos

Yes try maintaining Work centers in Internal tab with formulas defined in WC.

The PPB should display the duration after that.

Former Member
0 Kudos

Thanks to both of you,

I have already maintained work center in activity and formula is also maintain in work center capacity .

for scheduling we are not using formula we are giving manual value for duration.

for some activity, in graphical detail of network duration value is coming correct whereas for some its not coming correct.

Thanks.