on 08-08-2011 11:24 AM
Hi,
We are using Scheduling Agreement for Normal and subcontracting procurement.
Against Scheduling Agreement we enter the delivery schedule.
System allows to post the Goods Receipt even for back dated delivery schedule.
Can we restrict to post the Goods Receipt for back dated delivery schedule?
Regards,
Hai Niteen,
In case if you want to stop back dated delivery schedule,
Make the user exit in the delivery order
So system check
Planned GI date and Actual GI date should match else give a error message.
Regards,
Mani