Hi,

After executing CNE5 report it not showing BCWP value in particular project only.I have checked all the necessary data like actual dates are maintained.

What could be the reason.

Please guide.

Regards

Nitin

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member230675
Active Contributor
0 Kudos

hope you had run CNE1 before CNE5 to update the value.

Also reconstruct PS data base (CJEN) and check.

Former Member
0 Kudos

Hi,

Thanks for reply.

I've already done that.

BCWP is not showing only for 4 projects & in other project it is giving correct BCWP value.

When we generate MIS through BW Module I am getting BCWP graph for the same project whose BCWP not showing in CNE5.

Thanks & Regards

Nitin

Former Member
0 Kudos

Dear Experts,

Please suggest.

Thanks & Regards

Nitin

former_member225645
Active Participant
0 Kudos

Nitin,

As you know, POC is product of Actual POC and EV Basis(Plan or Budget). Pl check those two values are populated/maintained.