on 08-05-2011 8:31 AM
Hi,
After executing CNE5 report it not showing BCWP value in particular project only.I have checked all the necessary data like actual dates are maintained.
What could be the reason.
Please guide.
Regards
Nitin
hope you had run CNE1 before CNE5 to update the value.
Also reconstruct PS data base (CJEN) and check.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Nitin,
As you know, POC is product of Actual POC and EV Basis(Plan or Budget). Pl check those two values are populated/maintained.
Mathavan