on 08-05-2011 7:54 AM
Hi All,
While booking the Sales Order getting warning message like MRP area for 4000000310, not determined - continue with plant MRP aea for newely created plant only.
So that scheduleling not happening.
Kindly help me to resolve this.
Regards,
Saravanan E
Hi
I am assuming that 4000000310 is the material. I guess you have not maintained the MRP views in the material master for the material you have entered in the sales order.
Go to your material master and maintain the data for MRP 1, MRP 2, MRP 3 and MRP 4 views and then try creating the sales order.
Hope this helps.
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
in fact what is 4000000310?
Marian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Carry out Plant parameters in OMI8
Then click on COPY and copy from plant 0001
Kapil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.