on 08-05-2011 5:44 AM
Hello,
In our case for customer collaboration SNC5.1, the customer can receive the products on Tuesday and friday so we have assigned the time stream calendar according to this.
Our requirement is such that sometimes customer wants the products to be shipped only on Thursday.
so do we need to make another time stream ca;endar and assign it to location.
Is there any way to tackle this scenario.
Regards,
Vaibhav Virkud
Hi Vaibhav
Check the below thread, it should help you
If you are completely aware of the dates, during which customer requests on thursday.
You can manually change the periods in your shipping calendar, the fixed check box will not allow any automatic changes to the manually changed periods
/n/sapapo/calendar, Tab Periods
In this way you can avoid the two calendars...
Regards
Vinod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Vinod,
Issue is that of day. Now currently they only receive the goods only on tuesday and friday. So we have created the receiving calendar (Time stream) as per this.
Suddenly it may happen that the receiving day they would like change to Thursday.
Then do we need to create another time stream calendar and assign it to Location.
Regards,
Vaibhav Virkud
Hi,
As i understand you would like to change the delivery date very often. Then you can use only 1 calendar and re calculate the periords in it.
Also deleting a delivery date is also another solution.
As a last you can activate the TLB BADİ "/SCA/IF_EX_VTLB_ADAPT_EXT" and create a custom logic.
Best Regards,
Selim Batur