cancel
Showing results for 
Search instead for 
Did you mean: 

Cancel Change Number control in material master routing maintance?

Former Member
0 Kudos

Dear expert

In our company, we have PLM function and must enter change number in material master and routing screen

MM01/MM02 CA01/CA02,could I cancel this control and where is the configuration path in SPRO?

Thanks

Linfeng

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Kindly check in OS54.

Under Revision Level, unselect the check box Rev. Level active. If you want that automatic, you can go for Rev. Lev. Automatic. Before doing any changes in config, please explore pros & cons of the same.

For routing, in OP5A, set the field selection as Change Number - Input

[Change Management|http://www.sap-img.com/pp007.htm]

Regards,

Edited by: Maheswaran.K on Aug 3, 2011 10:27 AM