on 08-03-2011 3:58 AM
Hello Guys,
Can someone explain what is project version and its functionality. Can this be controlled with status flow of Projects. For example, In status flow, when PM changes to Update status an new version of project shoud be created.
Can this be possible in cProjects as standard functionality.
Thanks in advance...
Regards,
VJ
There are two types of versions in project management
1. Project versions: Typically used for reporting the state of a project at a given time. Yes it is possible to automatically generate a version based trigger on a project.
2. Simulation version : this is typically used to simulate a project. At times the cost planning, effort estimates needs to be determined which can be done using simulation versions
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.