Account integration problem with ECC 6.0

Former Member
0 Kudos

Hi

We have using PPM 5.0 system with ECC 6.0 system (No EHP). Problem we are facing is we are not able to created the PS project automatically.

I have done already all the necessary settings and in manual case it working fine it seems. I eager to know any suggestions on this to resolve, to achieve automatic creation of project.

Do you feel there is any issue with EHP?

Regards,

Pramod

Accepted Solutions (1)

Accepted Solutions (1)

amit_maheshwari2
Contributor
0 Kudos

Hi Pramod,

Refer to the note 1427365 for details. The pre-requisite for PS integration is as below:

SAP Portfolio and Project Management 5.0 SP02

and

SAP ERP 6.0 SP 17

or

SAP ERP 6.0 EhP2 SP07

or

SAP ERP 6.0 EhP3 SP06

or

SAP ERP 6.0 EhP4 SP06

or

SAP ERP 6.0 EnhP5

Regards

Amit

Former Member
0 Kudos

Hi,

Thanks for quick answer, we already have the required SP and references.

The problem is resolved now.

Regards,

Pramod