Plant field validation and mandatory field in CC master

former_member299514
Participant
0 Kudos

Can we have a validation of a field e.g. Plant in WBS level and substitution at the same time.

In projects Plant gets substituted during saving project from Cost center master data. At the same time can I maintain a validation that if this field is not updated it would would not allow save project.

Which one Validation or Substition is prioritized first during project saving?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

If both substitutions and validations (i.e. both can be used at the same time) during the save process, the substitution steps are first carried out step by step followed by the validation steps.

Regards,

Syed Ammar Zaheer

Former Member
0 Kudos

Hi,

I think it is possible to have substitution and validation at the same time. SAP document says " If you have defined a substitution that contradicts a validation condition, the system informs you of this by displaying a message. We can therefore say that validation has priority, or is u201Cstrongeru201D than substitution."

Warm regards,

Srinivas Potluri

Edited by: Potluri Srinivas on Aug 2, 2011 7:07 PM