Credit commitment of $49,918.12; Detail report does not show the same value

Negative Comittment

Project XXXXXXXXXX lists a negative comittment of $XX,XXX. Requesting negative comittment be cleared.

in report budget/actual/commt/rem.plan/assigned i dont know the tcode. in this report negative committment is showing instead of debit. how to clear and why it is displaying the value?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use the correction program RKACOR04. In this you need to give your controlling area and the object number of teh WBS Element (s) and select the check box for commitmnet and update. Once you execute this you have to follow it up with CJEN. This should remove the negative commitmnet from your project.

Regards

Sreekanth

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Could you please review note 152571? Also, please run transaction CJVC and delete any yellow and red flags for the cost elements. Once there is not any yellow or red flag in CJVC you could run CJEN as my colleagues have already suggested.

Thanks a lot and kind regards,

Enrique

Former Member
0 Kudos

Check the Costelement category of the cost element against which this negative commitment gets reflected.

Edited by: ravi kumhar on Aug 2, 2011 12:24 PM

Former Member
0 Kudos

Hi,

Try running RKACOR10 and then CJEN and check. You may also try RKANBU01, RKACOR04.

Regards,

Gokul