on 08-02-2011 6:53 AM
Ours is project based Engineering company, we mfg euipments for the client which is part of the project.
We define separate WBS element for equipment to be manufacture & create reservation under this WBS element.
Secondly we follow production process through PP & define BOM for equipment which contains component rquired to mfg the equipment. To control cost(budget) component group wise we create separate sub WBS element for each component group(plates, motors etc) under above equipment WBS element
Kindly refer e.g.below
1. Equipment (Finished code) to be manufacture is attached on WBS MYC-210952-06-03
2. Production order(1003780) created with reference to above WBS element
3 Material procured under WBS MYC-210952-06-03-001
4. Stock available under WBS MYC-210952-06-03-001
We would like to issue material available under MYC-210952-06-03-001 to production order which is attached to WBS MYC-210952-06-03. (Tcode MB1A)
System allows to issue stock, but gives budget error.
Is it possible to transfer budget auto in the transaction MB1A itself from MYC-210952-06-03-001 to MYC-210952-06-03 or what is the best solution available for above situation.
Kindly confirm.
Thanks & regards
Sanjay Karnekar
> We would like to issue material available under MYC-210952-06-03-001 to production order which is attached to WBS MYC-210952-06-03. (Tcode MB1A)
>
> System allows to issue stock, but gives budget error.
>
> Is it possible to transfer budget auto in the transaction MB1A itself from MYC-210952-06-03-001 to MYC-210952-06-03 or what is the best solution available for above situation.
>
Create a Z tcode and a BDC which will do budget transfer first then will do goods issue.
Otherwise use requirement grouping of material and assign budget only at level one just for overall control.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjay,
Try and see the Budget available in the WBS where you want to transfer the material. If availabe no issue or else please transfer the budget from the WBS where the stock is availabe to the Other WBS where the stock need to be updated through tcode: CJ34. Then do the trnasfer the material from one WBS to another using 415 q moment type.
Thanks
Regards
kishore
Hi Sanjay,
You have consumed a budget at lower level WBS for material procurement. And at upper level you want to do stock transfer.
But while doing budget allocation you have distributed the budget from Upper level to lower level so there is no distributable value is avaialble at upper level for the amount of the materail stock you want to transfer.
In this either you have to keep your all budget values at upper level where your doing equipment aeembly and not distribute the budget further at lower level.
Now you alredy this so you cant do anything.
Now you have following option available with you. You have perform following activity by the given sequence.
Deactivate the Budget check by CJBW
Do your stock transfer
Do budget return by CJ38 from level WBS to upper level WBS
Now Activate the budget check by CJBV.
regards,
Pradeep
Hi,
Firstly, check the standard reports on Budget that are available. Try to find out the available budget that you have for the relevant WBS's. Based on this you can decide whether you need to carry out any budget updates. This is one way of resolving this. There are other ways but they act only as a workaround and i would not suggest to go for that.
In addition to this you can also search the forum and find relevant threads that address this issue.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Gokul
Thanks for your reply
As I mentioned , our requirement is material issue from one WBS element to another WBS(of production order). We do not want to add additional budget since it is already consumed for sub WBS element. Now when we are trying to issue material same budget should transfer from one wbs to another. In short our cost is getting transferred from one WBS to antoher WBS, there is no additional cost.
Regards
Sanjay