on 08-01-2011 12:54 PM
Hi ,
I am an SD consultant and quite new to PS. Please execuse if my question is basic.
When i am creating a template in transaction CJ91 system is defaulting the "Project Profile (Proj-PROFL) " value as "DPSC1" and that filed is in grey mode. I couldnt make changes to that filed" .Can some one let me know which setting controls this and what makes system to default a value for this field.
Also could you let me know on the significance of these fields "Project Profile (PROJ_PROFL) and WBS status Profile (Proj-STSPR).
Thanks in advance,
Srini
Are you creating thiby copying an eixsting template? If yes the behaviour is correct as the project profile will get copied from the template you are using to create a new template. As far as your second question goes, i would suggest you to go through SAP Help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sreekanth and Gokul,
I will assign project profile "DPSC_T1" to my new template , still I copy it from another template which is with the profile "DPSC1". When I tested in our sandbox in CJ91 initial screen i can specify a different project profile and in the column STD Proj defintion i give a template name which has different Project profile.System is allowing me to do so
Will there be any negative impacts going with this option?. Please suggest
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.