Project Actual End Date cannot be entered

0 Kudos

project template looks like this

PROJ DEFN: PROJ-A

WBS COMPONENTS: PROJ-A-1

WBS COMPONENTS: PROJ-A-1-A

WBS COMPONENTS: PROJ-A-1-B

PROJ-A-1-A & PROJ-A-1-B have actual end dates. But PROJ-A-1 is disabled.

thanks

Accepted Solutions (0)

Answers (4)

Answers (4)

0 Kudos

thank you

Former Member
0 Kudos

Check the status of the said WBS as mentioned by Abdul. You can also schedule the project and check if that helps.

former_member230675
Active Contributor
0 Kudos

. But PROJ-A-1 is disabled.

Did you release this WBSE.

Former Member
0 Kudos

Have you tried checking the log for locked objects? Please ensure whether you are getting this error because of authorization controls implemented in PS.

Also have you tried using date functions to roll up dates from lower level WBS to the top?

Regards,

Syed Ammar Zaheer