Req. flowed back into SOCO (SRM) despite a POis processed

Former Member
0 Kudos

Hi All

We are on SRM 7.0, EXTENDED classic scenario and we are experiencing the following issue. please provide your sujjestions

Req. flowed back into SOCO (SRM) despite a PO attached to it. We have been noticing that req.s flow back into the SOCO even though we have already processed them

Thanks&Regards

BK Myneni

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please make sure that clean req req program is up and running and also check the configuraton settings for specified product categorya nd followin documents creation settings in SPRO.

Regards,

Krish

Former Member
0 Kudos

Hi Krish

Many thansks for your valuable sujjestion

I checked the program and also the prod category settings in SPRO. i belive system is generating multiple PO against single requesition!!

Thanks

BK Myenni