Statistical forecast varies in back ground and foreground !

former_member224276
Participant
0 Kudos

Hello friends,

When i generate the Statistical forecast at *product and plant* level in foreground it gives some values, then generate in background at *product and plant level* again it gives different values.Could you pl through me some lights on me.

Regards,

siva

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187488
Active Contributor
0 Kudos

Hello Siva,

Maybe you have different aggregation level for your foreground forecast and background job.

Please first check your 'aggregation level' setting in /sapapo/mc8e.

Or maybe you're using different forecast profiles for your foreground and backgournd.

Please check the settings in /sapapo/mc8t of the forecast activity.

Do you have "always use job profile" setting on?

You can also check the background run's result in SM37's spool file, to see on what level did it execute, and what forecast profile it used for each planning object.

You can check note 372939 to compare the results. In this note, you will have great tips on how to compare both results. Besides that, note 374681 will give you detailed information on how to have the selections when using mass processing.

Also, check the note 546079, which contains more informations on how to have Interactive and batch forecast to run equally.

Best Regards,

Ada

Edited by: Ada Lv on Jul 29, 2011 3:22 PM

former_member224276
Participant
0 Kudos

Thanks for you quick repley.

Foreground: In my selection id product and plant level I am useing.version also same in selection and job.

background also same level useing.

in both cases useing waighted moving agerage model.

in sm37 it shows STR14,there is no aggregation level.

in my activity i did not check the "always use job profile"

former_member187488
Active Contributor
0 Kudos

Hello,

Do you have only one location and one product?

SM37 does not show explicity the aggregation level, but it shows the planning objects.

You can get information from there.

Sorry I have to idea regarding 'STR14'. If you like you can post some content in spool file.

If you do not check "always use job profile", please check whether you have other assignment in /sapapo/msdp_fcst2.

I suggest you to use this option in order to compare the results of foreground and background.

Best Regards,

Ada

former_member224276
Participant
0 Kudos

Hi Ada Lv,

In SAP NOTE 372939 step 3

3. In the time between executing the two forecasts the forecast profile

could have been changed. Note here that the forecast profile is also

generally saved as well when you save data in interactive planning.

Thus, for example, when you work for another selection with the same

forecast profile, change some parameters and save the data, then your

forecast profile can also be changed.

with this help i can solve my problem

thanks for you help.

Edited by: sivaram2411 on Aug 1, 2011 2:31 PM

Edited by: sivaram2411 on Aug 1, 2011 2:32 PM