Error for Project finish date earlier than forecast finish date

Former Member
0 Kudos

Hi Experts

I have the dates in Project definition as follows:

Forecast start (PROJ-SPROG): 31.01.2011

Forecast finish (PROJ-EPROG): 31.03.2011

If i enter date 30.03.2011 as Finish date (PROJ-PLSEZ), below error message appears: "Finish date is earlier than start date. CJ563"

The date i have entered is later than PROJ-SPROG, still not accepting.

It accepts entry of date beyond the date in field PROJ-EPROG.

Can anybody share thoughts on this?

Warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Can you kindly verify the other sets of dates being maintained in your activity (i.e. earliest & latest)? Are you using default configurations for PS i.e. confirmation dates are checked against basic dates and not forecast dates?

Regards,

Syed Ammar Zaheer

Answers (0)