on 07-28-2011 6:38 AM
Hi Experts
I have the dates in Project definition as follows:
Forecast start (PROJ-SPROG): 31.01.2011
Forecast finish (PROJ-EPROG): 31.03.2011
If i enter date 30.03.2011 as Finish date (PROJ-PLSEZ), below error message appears: "Finish date is earlier than start date. CJ563"
The date i have entered is later than PROJ-SPROG, still not accepting.
It accepts entry of date beyond the date in field PROJ-EPROG.
Can anybody share thoughts on this?
Warm regards
ramSiva
Can you kindly verify the other sets of dates being maintained in your activity (i.e. earliest & latest)? Are you using default configurations for PS i.e. confirmation dates are checked against basic dates and not forecast dates?
Regards,
Syed Ammar Zaheer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.