on 07-27-2011 3:59 PM
Hi,
I have configured a network user status to 'prohibit Material purchase requisition'.
This works when trying to create a requsition in ME51N - but still allows me to create a PR in CJ20N.
Can anyone think of why it would allow me to create the PR in CJ20N when the status is set?
Thanks
Hi Henry,
Please refer Note 497090 - Blocking purch. orders/requisitions/commitment from networks.
I think it will not be possible to achieve the required result thru CJ20N.
Warm regards,
Srinivas Potluri