cancel
Showing results for 
Search instead for 
Did you mean: 

Posting in Miro with Po getting an error Item 003 Ntwk actvty budget Exceed

Former Member
0 Kudos

Hi Gurus,

While posting in Miro with PO i am getting an error Item 003 Ntwk actvty 5016609 0010 budget exceeded

Availability control:

Please check and do the needful.

Regards

Laxmi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check the budget allocated to the project / WBS as it seems it is not sufficient. Make necessary updates.

Regards

Sreekanth

Former Member
0 Kudos

Hi

Thanks for your reply

Can you please help with T code where to check the Budget,Can you explain me

Total plan cost : 53.049,94 0

Total Actual Cost:00

Plan/Actual Varians : 53.049,94-

Laxmi

Former Member
0 Kudos

Hi,

Use the report S_ALR_87013558. This will show you the Budget, actual and commitmnet. You can see the original budget in CJ30 or IM52 if you are using IM.

Regards

Sreekanth