Hi Experts ,
Our projects are make to order scenerio.
We foud that plan cost is not getting picked up from Production orders in the S_ALR_87013542 report . Although production order shows plan values against material & labour , still plan cost does not appear against wbs in the S_ALR_87013542 report.
As far as other plan cost are concerned like internal activities cost, primary cost & sales values are appearing properly in the above report.
Please guide me to resolve this matter .
Thanks & Regards,
Vishal Murmoo
check for appended indicator in OPSV for production order - order category.