Earlier date in finish date field than the forecast start date (in Proj def

Former Member
0 Kudos

Hi Experts

I have foreast start and forecast finish dates maintained in Project definition. N dates in WBS elements.

However I am able to maintain an earlier date (than forecast start date) in Finish Date field in PD.

I believe there should be a validation with dates.

Please provide clues.

Warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

I am getting error when i enter start date earlier than finish date.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please create a validation rule with all prerequisites, check and message .Assign it to the project profile. For the running project , open the project in CJ20N ,--> Edit -->Validation and select this validation for the system to respond appropriately.

Warm regards,

Srinivas Potluri

former_member203108
Active Contributor
0 Kudos

I dont think you need to set up a user validation for this. It is already available in Std SAP. You should get this error

Finish date is earlier than start date . Message no. CJ563

Former Member
0 Kudos

Hi,

As per the question posted, user wants to validate between Forecast start date ( SPROG) and Finish date ( PLSEZ) . Hence validation may be required. ( May be a typo error in the question )

Warm regards,

Srinivas Potluri