Dear Sir,
With the help of QM procurement key we are resctricting vendor payement for quality inspection to complete but once the quality inspection is completed system doesnot automatically releasing the MRBR payement block as it logically should be.
Will you please help me in this regards.
Edited by: mihir.eng on Jul 26, 2011 12:47 PM
system doesnot automatically releasing the MRBR payement block as it logically should be
As I understnd After usage decision system allows to make payment & remove the block due to Quality in MIRO.same data should be reflected in MRBR !!