part of a SC item carried out sourcing , another part can be sourcing too?

Former Member
0 Kudos

we used SRM 7.0.

part of a SC item carried out sourcing , another part can be sourcing too?

for example , SC item 01 which include 1000 pc A.

1st, we create RFx reference item 01 with 600 pc A

2ed, can we create another RFx with remaining 400pc A ??

regards

claud

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I don't think your scenario is offered by standard SRM sourcing functionality. Sourcing cockpit would not let you create "partial quantity" follow-on document. Even if you create the follow-on document, e.g. RFx or PO draft and change the quantity to be less than originally in the SC item, the whole SC item is already marked as a whole as not sourcing relevant (PO case) or RFQ created, which means you can't source the item any more, even though you have left over quantity on it.

Answers (1)

Answers (1)

Former Member
0 Kudos

i test this scenario.

1st , i create SC: 100 matA

2ed, carry oout sourcing ,create PO with part of material: 60 matA

3rd after carry out programme'CLEAN_REQREQ_UP'.

4th the remaing quantity 40 matA appear in the sourcing cockpit.

so , the key point is the programme 'Clean_reqreq_up'

Former Member
0 Kudos

Hi Claud,,

Jay is absolutely right. You cant source the item even if you have left over quantities. Infact I was curious to try out your scenario and for me it did not work out like you mentioned. Once I created a PO for 60, I could not find the SC back in SOCO for the remaining 40. Wondering how you managed it.

Regards,

Nikhil