we have two company codes & two plants in company code A plant A1 we will manufacture all the material required,
in company code B plant B1 we will take the order for erection of structure & supplying material to customer's site
in this case sales organization of CC "B" will raise the sales order by putting the plant A1 of company code A then in that case
sold to party , bill to party , payer is Company code B & ship to party is Customer.
this is inter-company sales scenario.
now after receiving the material at customers site company code B will charge the customer for services provided for erection of structure & for the material provided by the plnt A1 of company code A
how to map the scenario
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Process is like this
Company B takes material from company A, plant A and supply to customer 12345
so for company B customer is 12345 and for company A, B is customer
Process in company code A
Create sales order for customer 12345 (put plant B as delivering plant) >>> Delivery from plant B >>> Create invoice for customer
Now company A will raise inter company invoice to company B (for provided material)
Kapil