Commitments Overstated on Project System Report

Former Member
0 Kudos

ECC 6.0 SAP system - Ran PS report S_ALR_87013533 and the same PO values were in actual spending and commitment columns. The value was on the initial screen but when you drilled into commitment column the values indicated $0. Ran CJEN for individual WBS and issue was corrected. Is there an issue with running the CJEN transaction on all WBS elements on a periodic schedule or should it just be ran for individual WBS elements on an as needed basis?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I would suggest to run CJEN on need basis, than a wide open range frequently to avoid impact on system performance.

Regards

Sreekanth