Dear All,
Pl. clarify that by using Tcode: T_56 we have defined Transport Settlement Purchase Order Generation period as C (Generate purchase order for validity period of 1 month).
Here 1 month means
1 Month = From 01-Jan-11 to 31-Jan-11
or
1 Month = 30 Days (PO genereated on 5th Jul-11, it will effect upto 4th Aug-11)
which one is correct meaning, pl. clear my doubt.
Regards,
Saravanan E
Hi,
The one month here would be the date from of your PO creation date, based on the system time.
Please refer to [SAP Note 506605|https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=506605] for more information on which date is considered when the PO is triggered.
For the field being consider, you can refer to [System field for date and time|http://help.sap.com/abapdocu_70/en/ABENTIME_SYSTEM_FIELDS.htm]
Hope the above helps.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
Tkz for your information
Regards,
Sarran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.