can i define PV in SPRO(Customizing) instead of MM-MRP4 view

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Soumyakant.

Why do you want to use SPRO to create production version instead of MRP4?

You can create production version using transaction C223 instead of MM-MRP4.

Regards

Thiago Cyrillo

Answers (3)

Answers (3)

wilian_segatto
Employee
Employee
0 Kudos

Dear friend.

I would say /C223 is the most used transaction for maintaining Production Versions.

There you can add an entry for your material, add BOM number, group counter, etc.

Don't forget to perform a "Check" in the lower section so you have a green light appearing on the PV entry.

Hope this helps you!

Will

Former Member
0 Kudos

Thiago and Sujit..

Thanks for your reply

I know about mrp4 and c223, " what i had doubt is, wheather in customizing I can maintain any PV or not "

I guess, these are the only 2 procedure in which i can create it.

Former Member
0 Kudos

Dear Soumyakant,

For your specific question - the answer is no... one cannot set the PV in customising.

As you rightly know only 2 ways are available to maintain PV.

Regards,

Sujeet Kulkarni

Former Member
0 Kudos

Dear Soumyakant,

You don't have to configure anything for production version separately.

Basically production version is a master data where in one maintains relation of BOM & Routing for that material. This is applicable for a particular range of lot size. Also production version can be checked for correctness of data maintained.

Either you can create it through MM02 (MRP4 view) for a single material or you can create it for mass in transaction C223.

Hope this clears your doubt.

Regards,

Sujeet Kulkarni