Hello,
Does anyone have experience of using SNP/CTM for planning decisions of optimum raw material lengths to use for production?
Eg. whether to use 2 x 2m metal bar stock or 1 x 4m bar stock.
How should raw material inventory best be managed to support this?
We use only CTM at the moment in a discrete manufacturing environment so this is something new.
Regards
dhe999
Hi,
for that I would recommend to use Characteristics-Dependent Planning (CDP)
[Characteristics-Dependent Planning (CDP) |http://help.sap.com/saphelp_scm70/helpdata/en/b1/947337e68ae526e10000009b38f889/frameset.htm]
CTM can now also do Planning with Characteristics.
[Planning with Characteristics |http://help.sap.com/saphelp_scm70/helpdata/en/e1/bb867841e14927a7aef44393e12991/frameset.htm]
BR Frank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.