Planning Consumption by length, eg Bar Stock in Metal Fabrication Industry

Former Member
0 Kudos

Hello,

Does anyone have experience of using SNP/CTM for planning decisions of optimum raw material lengths to use for production?

Eg. whether to use 2 x 2m metal bar stock or 1 x 4m bar stock.

How should raw material inventory best be managed to support this?

We use only CTM at the moment in a discrete manufacturing environment so this is something new.

Regards

dhe999

Accepted Solutions (0)

Answers (1)

Answers (1)

frank_horlacher
Employee
Employee
0 Kudos

Hi,

for that I would recommend to use Characteristics-Dependent Planning (CDP)

[Characteristics-Dependent Planning (CDP) |http://help.sap.com/saphelp_scm70/helpdata/en/b1/947337e68ae526e10000009b38f889/frameset.htm]

CTM can now also do Planning with Characteristics.

[Planning with Characteristics |http://help.sap.com/saphelp_scm70/helpdata/en/e1/bb867841e14927a7aef44393e12991/frameset.htm]

BR Frank