Hi Experts,
I need your assistance.
My client has created a project and allocated budget manually and released (in billions). Actual cost is posted for some WBS elements and commitments are also there for some WBS elements (in thousands). Due to drawing changes, budget allocated to these WBS elements is not valid and management wants to delete this budget. Rest of the project (WBS Elements) will continue.
How to go about this?
Thanks in advance.
Regards,
Murthy.
Edited by: R.S.V.R Murthy on Jul 22, 2011 8:52 AM
Hi,
Please use SAP Note : 1145955
Thanks
abdul.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abdul,
is this SAP Note applicable where actual and commitment postings are done.
actually my client wants to remove Budget from lower level WBS except level 1. they want to track budget and control at level 1 WBS only so need to delete but actuals are there so we are unable to delete budget and reset BUDG status.
please help
thanks
Sunil
Hi Sunil,
I am not sure but try to transfer the actual cost from lower wbs elements to other WBS elements/other cost objects and then re post them back to level 1 wbs element then check if system is allowing you to remove budget from lower level wbs elements and reset OPSX. I think if commitments and actual are removed from WBS then it can be possible to reset the BUDG status of wbs. Though I am not sure of it but I would suggest you to check it once if it is possible and let us know if it works to some extent.
Regards
Saurabh
Thank you all........
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can return the budget by using following transaction codes.
CJ38 - In Project
CJ35 - From Project
only available budget can be return from the respective wbse's. so here you can return unwanted budget from the project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Murthy,
Since you are using Budget Releases, You will have to first reduce the Released budget in CJ32. Then only you will be able to reduce the Budget. ( If Annual/Overall Budget is less than the Released Budget, then obviosly the system will thow an error ).
Hope this helps,
Srinivas Potluri
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.