Dear experts,

Can somebody guide me how to restrict an equipment from production planning while that machine is under preventive maintenance.

Thanks & regards

R.A.V

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Equipments r part of PP Work Center, in eqpt master record IE02 , u need to maintain PP Work Center as well as PM Work center and when u create MO or generate preventive order on that eqpt , if u put system condition in Order as O - Reserved for maintenance , then PP Work center capacity gets blocked .. , now if u create a PP Order at same time , system will allow you to create a production order and if u have a capacity availability check in PP Order while releasing , u can block the release of the pp order ..

So in transaction OIOI for business view 2 in capacity availabilty un flag the no check, give Overall profile and make release Order as 3- No release if Capacity in not sufficent ..

try the above and check if it meets u requirement ..

regrds

pushpa

Former Member
0 Kudos

Issue resolved and closed.

Thanks to all