Milestone Invoicing Plan Issue

Former Member
0 Kudos

Hi All,

We have successfully configured Milestone Invoicing Plan Scenario, but are facing one issue. We were successfully able to transfer PS invoicing plan to PO. After milestone is confirmed when we go to check PO in DISPLAY mode, block is still there. If we just switch to CHANGE mode in PO without doing anything else, the block disappears. Hence the functionality appears to be working but we have to switch to change mode and save PO once.Please let us know if anyone faced this issue earlier and what was the resolution.

Thanks in advance.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Ankesh,

It's the standard behavior in SAP. Contacted OSS.. no help. finally with the Help of WF and PO maintain BAPI we made that to Work

Former Member
0 Kudos

Awaiting for Valuable Responce.

Kindly let me know the solution !

Former Member
0 Kudos

Better to raise a message to SAP i guess.

Former Member
0 Kudos

Awaiting for Valuable Responce.

Kindly let me know the solution !