cancel
Showing results for 
Search instead for 
Did you mean: 

Bin search for putaway

Former Member
0 Kudos

Hello, experts!

Could someone give advice on following situation:

1) the storage type (high rack) has put away strategy P- storage unit type, mixed storage is set A- Several homogeneous storage units per bin, the mixed storage has value X - Addition to existing stock permitted.

2) material master has mark Addition to existing stock allowed.

When creating TO to move some returned quantities to stock, system is not searching for bin with existing stock. It adds the quantity to first available bin, where storage unit is allowed.

Is it possible to set system first add to existing stock without using strategy " I ", since mixed storage is not allowed for this strategy?

Thanx in advance!

WBR,

Brucke

Accepted Solutions (0)

Answers (1)

Answers (1)

christian_rosa
Employee
Employee
0 Kudos

Hi Brucke,

It is hard to diagnose without full information however you can try to find out which strategy it is executing by setting a

break point in the include LL03AF0B in the line PERFORM STRATEGIEN. Then try to trace LTAP-VLPLA: Source storage bin when you get into LL03AF1F you will see then the bin search strategy and why was that.

I hope to have helped you.

Best Regards,

Christian Rosa