Not able to close project:

former_member219195
Participant
0 Kudos

While closing a level 1 WBS, we are getting error message "Incoming order value not settled in full"

However for this project, All WBS below level-1 are closed and for level 1 WBS, no operative indicator is selected.

Not billing/ Planning or account assigned.

Also there is no order attached to this WBS element as wbs element is not a billing element.

Strange thing is now billing element indicator is gryed out.

So we could even not carryout CJA2/ KKA2 as this is not a billing element.

Also we could not reverse CJA2 as system gives error that WBS is non billing element. and we could not set it as it is gryed out,

CJI3 shows balance zero.

Also WBS settlement parameter we could not bring in edit mode so that we could change those.

Please assist how we could remove this error and close the WBS.

regards, madhu

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Madhu,

Try CJEN. It may solve the issue.

Warm regards,

Srinivas Potluri