Hi,
We have a WBS element at level 4 in a project. PRPS also shows the level as 4 but structure reports CN41N or cost/budget related S_ALR reports show that WBS at level 3. There seems to an inconsistency, can anyone advise how this inconsistency be corrected.
Thanks in advance.
Regards,
Mohammed T Haque
Hi,
run CJEN transaction for reconstruct project info database for your project definition & then check.
Regards,
Sandeep