on 07-18-2011 9:57 AM
Dear Friends
Can anyone explain how rescheduling of sales order quantities can be carried out? For eg. Consider already 100 pcs of a material is allocated to sales order # 1`. Now, another sales order # 2 is created & this has high priority. Now, how do we allocate the 100 pcs (which is allocated to sales order # 1) to this sales order # 2?
Any light on the above?
Rgds
Sumanth.G
Hi
You need to run the transaction V_V2 for rescheduling in SD.
Please go through these link for details about rescheduling and backorder processing:
http://help.sap.com/saphelp_46c/helpdata/en/e6/4a79ec9e0311d189b70000e829fbbd/frameset.htm
http://help.sap.com/saphelp_46c/helpdata/en/e6/4a79ec9e0311d189b70000e829fbbd/frameset.htm
Hope this helps.
Regards
Madhu
Edited by: Madhu Naidu on Jul 18, 2011 11:21 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If you unticked "Include Sales reqmts" in OVZ9, then when you do availabililty check for the second order, stock will get confirmed to second order.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.