Hi friends,

Kindly help me for Prerequisite statement for below substitution requirement.

Substitution Requirement - In CJ01 or CJ02, when we assign or change the Person responsable at any WBS level and enter or save then this change need to effect for lower levee WBS elements.

So I am using " PRPS- VERNR field is substituted by RCJ_PRPSUP-VERNR" by selecting Filed Filed assignment.

This substitution need only for Engineering projects. That is the project which contain project profile PR001, PR002 and PR003.

I need the help for defining Prerequisite statement for the substitution.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

This will not work by substitution rule. can be achieved thru WBS BADI implementation -( WORKBREAKDOWN_UPDATE)