how to move the task within the hierarchy in sap cproject

Former Member
0 Kudos

HI ALL,

how to move the task within the hierarchy.

for example: aaaaa----


project

bbbbbb-------phase

1test------task

2test-----task.

i need to move the task 2test above 1test like below.

aaaaa----


project

bbbbbb-------phase

2test------task

1test-----task

how to do this.

Thanks in adavance,

Kumar.p

Accepted Solutions (1)

Accepted Solutions (1)

schneidertho
Advisor
Advisor
0 Kudos

Hi Kumar,

you should be able to do this with the sort number of the tasks.

Regards

Thorsten

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

This is the standard functionality in SAP PPM 5.0.

You can drag and drop the task from any postion to any postion.

Regards,

Nitin

Former Member
0 Kudos

Hi Kumar!

If you're using PPM 5.0, you can also select a task and move it within the project hierarchy ("drag and drop" functionality).

Regards,