Hi,
I am facing problem in Project progress report CNE5.
System is calculated 300 % poc in Adjusted aggregated actual POC & Aggregated actual POC field only after full confirmed the activity (Degree of Processing is showing in report as 100%).
If I confirmed 50 % then system is showing above value 0% .
Also while CNE1 system is taking default method as :SAP 0-100, so i changed it into activity by 00006 (Work) then system calculate the Progress but only after full confirmation, but again it is 300%. which should not.
The configuration settings are as
1. Progress Version: -
Progress Version : 100
Plan Version : 0
EV Basis : 1 ( Cost Plan)
POC weighting : 4 Work, Basic ( Active Project)
2. Group of Progress version:-
Controlling Area & 1
3. Assign Progress Versions to Group Progress Versions:-
Controlling Area, 100 & 1
4. Define Statistical Key Figure for Percentage of Completion:-
Usage SKF (with unit of measurement= %)
Controlling area 1 10
Controlling area 2 20
Controlling area 3 30
5. Define Measurement Methods:-
Measurement method :0000000006 (Work)
Meas. technique : E ( Degree of Processing)
Max POC : 100
6. Define Measurement Method as Default Value
Progress version(100), Object Type (2:Activity, Internal Processing), Plan/ Actual( 1 &2 :both), Method (00000006 :Work)
7.Maintain Assignment of Cost Element Group
Cost element (PS) , Default selection( Yes) & cost element group(PS_PROP)
I hope above information is sufficient.
My problem is system is calculating poc only after full confirmation but i want at partial confirmation. Also after full confirmation poc is showing 300% which i want 100%.
Regards,
AVI
Hi Experts,
I am waiting for your valuable inputs.
Regards,
AVI
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.