Transit time calculation Route

Former Member
0 Kudos

Hi,

I have an issue in determining the delivery date for an STO.

My route is maintained as XXX--02 which is 2 days transit time and is correctly getting determined in the STO, however the delivery date is not correct on the STO

Order created date is 11th july

Material availability is 12th July

trnspt pllng/Load date is 12th July

Goods issue date is 13th July

Considering 13th july as goods issue date and route with 2 days transit time should determine 15th july as the delivery date, however I am getting 14th july as the delivery date instead of 15th.

Can you please let me know if this is something that you have seen before? and any suggestions.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please check if delivery scheduling is active and 2 days has been defined in route determination under transit time.

The planned GI and Actual GI dates also play an important role in delivery date determination.

If you are just creating a sales order create a delivery for it and check what is determined.

Regards,

Amit