on 07-13-2011 4:28 PM
Hi,
We have a Job X scheduled to run on 23:30 hrs everyday. The run of the Job varies from 15 min to 45 min. Now as per Business need we are to schedule a Job Y that runs immediately after finish of Job X. We have another criteria, which is the Job Y should run the following day and not the present day.
So, if Job X finishes on current day then Job Y too runs on the same date.
Is there a way in which, we could combine both the Time driven and Even Driven option together and schedule the Job Y.
Job Y checks that Job X got finished and if date is current date it waits and runs the following day at 00:00 hrs.
Job Y checks that Job X got finished and if date is following day it runs immediately.
Please suggest.
Regards,
Subhram
[How to run chained jobs|http://wiki.sdn.sap.com/wiki/display/Basis/Howtorunconsequentorchainedbackground+jobs]
Hope it helps
Regards,
Nick Loy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.