Implementing work time for shipping points

Former Member
0 Kudos

Hi,

I was trying to implement work hours for shipping points and has come across a weird issue. Once I define working shifts , the calculated PGI date is one day early,

Example:

Without work shifts for shipping point

Customer requested date - 08/26/2011

Route -2 day truck

No pick pack /loading time

I get a PGI date of 08/24

Work shift of 06:00 to 14 :00 hrs defined for shipping point, everything else remains the same:

I get a PGI date of 08/23 , 14: 00 Hrs.

The users are not happy with this; does anyone have a clue as to why SAP behaves in this manner and what is the business reason behind this calculation ?

Thanks,

Hari.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

I think I figured this out. A route of 2 days , demands a PGI at 00: 00 hrs on 08/24, as this is not a valid working time for the shipping point, SAP is moving it back to 14 hrs on 08/23 ( closing time on previous day).

Former Member
0 Kudos

HI,

It basically depends on the working times, shifts and factory calendar.

If your PGI falls on a Sat or Sun then SAP would calculate the PGI date on the subsequent working day.

Regards,

Amit

Former Member
0 Kudos

Thanks, but my issue is I am getting a PGI date which is one day earlier than Dock date - Transit.