on 07-12-2011 7:21 PM
In regards to a Material Master for a Maintenance storeroom Material, On the MRP 2 tab there is a field called Safety time/act.cov.
What is the difference between that and the planned delivery time of a material. I have tested both and they appear to do the same thing in materials planning. Can you tell me the differences between these 2 fields
Thanks
HI Yocoma,
The first difference I can site is that is in Workdays whereas Planned Delivery time is in Calender Days and is based on past experience
For further details please go through these links
http://help.sap.com/saphelp_45b/helpdata/en/f3/dbbb16b36111d1a6770000e83235d4/content.htm
http://help.sap.com/saphelp_470/helpdata/en/f3/41b53c4d36265ce10000000a114084/content.htm
Hope this helps!
Thanks,
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.