Material Master for Maintenance material

Former Member
0 Kudos

In regards to a Material Master for a Maintenance storeroom Material, On the MRP 2 tab there is a field called Safety time/act.cov.

What is the difference between that and the planned delivery time of a material. I have tested both and they appear to do the same thing in materials planning. Can you tell me the differences between these 2 fields

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

HI Yocoma,

The first difference I can site is that is in Workdays whereas Planned Delivery time is in Calender Days and is based on past experience

For further details please go through these links

http://help.sap.com/saphelp_45b/helpdata/en/f3/dbbb16b36111d1a6770000e83235d4/content.htm

http://help.sap.com/saphelp_470/helpdata/en/f3/41b53c4d36265ce10000000a114084/content.htm

Hope this helps!

Thanks,

Ravi