07-12-2011 2:57 PM
The RP type has been set as "RF".
A forecast run has been executed.
User realized that POS sales has not been updated for 1 day in the last week.
The current week forecast had been run
User perform the POS sales update after the initial forecast run.
Now, after posting the sales, User want to re-execute the forecast as it would give a more accurate consumption forecast.
How can User re-run the forecast in MP30.
Thanks
07-13-2011 4:49 PM
Hello,
If the forecast is run for the current period, they can rerun forecast for the follow-on period either using MP30 or MP38.
This could be better than Initializing the forecast (MM42) and rerunning it.
Thanks,
Venu
07-13-2011 5:05 PM
it is possible to re-run in MP30 for the same period again.
I tried but it's doesn't seems to execute again.
Please confirm
08-15-2011 3:27 PM