on 07-12-2011 6:35 AM
Dear Friends,
though i have not enter anything for the transit time , i found that in TVRO table TRAZT is getting update 1 for the routes, i have only ented transit duration , it is getting updated fine in filed TRAZTD.
in discriotion it is saying tha TRAZT is outdated, can you please let me know what is this fields implacts and how it gets updated at table level. when i check in route display mode except transit duration i have no other fields.
Ex:
entered transit duretion is 3 days it is getting updated in TRAZTD
no filed found in route for Tranist TVRO-TRAZT but this is getting updated always 1 for all new routes.
Can you have a look and let me know why this is happend ASAP.
thanks
raju.
Dear
Can any one clarify me from ware TVRO-TRAZT field getting updated, i did not fine this fild in the 0VTC trasaction but 1 day is getting determined.
Thanks
Raju.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether you have maintained any planned delivery time for the material in vendor -material Purchase info record.
regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.