cancel
Showing results for 
Search instead for 
Did you mean: 

Activities no longer viewed once projects are tagged as TECO

0 Kudos

Hi,

How come activities are not viewable once projects are set to technically complete? Our users would like to refer to the projects even after it has been completed.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

System display TECO'd network activities also and its not an issue. Dose user/users have authorization issue?.

Regards,

PSR

Answers (2)

Answers (2)

0 Kudos

thank you!

Former Member
0 Kudos

Hello Gerardo,

I have exactly the same question as you.

I am curious to know if you received an answer, before you answered "Thank you". Is it possible that there is a message missing from the thread?

Thank you in advance

former_member230675
Active Contributor
0 Kudos

please provide more details

0 Kudos

Once a project is set to TECHNICALLY COMPLETE, Materials used in the project can no longer be viewed. While there it can be viewed via Project Bulder(CJ20N), other reports such as CN52N no longer displays the material consumption. What users want is a report that displays the material consumption even if the project is TECO'd.