We have a wbs element <operating expense cost collector-Investment> the receiver mapped in CJ20n is AUC it is supposed to be cost center.
I already mapped cost center and But i am not able to remove AUC as receiver as it was greyed-out. It says "Rule cannot be deleted".
I tried to reverse settlement posted to WBS but still the same.
Appreciate if you could advise me on how can i remove the AUC as receiver. We need cost center as receiver.
Thank you!
Eve
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the settlement rule input the current period in the "To Period" column and input the current year in the "To Year" column. Create a new settlement rule with receiver as Cost center and go ahead. This should solve your issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can put the "To Period" & "To Year" and close this distribution rule and open a new one with the receiver of your choice.
Regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.