vinoth_g
Explorer
0 Kudos

Hi,

How to see the details about the change in profit center / cost center in a project and cost already posted to the older profit center/cost center.

Thanks

Vinoth G

Accepted Solutions (0)

Answers (3)

Answers (3)

vinoth_g
Explorer
0 Kudos

Hi Virendra & Nag,

Thanks for your reply.

Change doc is active in Project Profile under status management.

But am not getting any change docs in CN60.

Suppose there are 1000 Projects, out of which the user has changed the profit/cost center for 100 project.

I need to find out those 100 projects out of 1000 projects and for those 100 project whats the cost posted against the older profit/cost center and the new profit/cost center.

Thanks

Vinoth G

former_member203098
Active Contributor
0 Kudos

excute cji3 for the project where cost/profit center has been changed. choose the cost center field from the layout, there

you can find the list of cost centers (old and new) for given project.

regards,

virendra_pal
Active Contributor
0 Kudos

If you activate change docs in project profile then you can see the changes in the project via CN60

The use KSB1 to see the postings on both old and new cost centres

former_member203098
Active Contributor
0 Kudos

run the report KSB1 with old cost center with posting dates.

regards,