on 07-10-2011 2:01 PM
Hi,
I am loading a key figure from info cube to planning area. The quantity after loading into planning area is less than the info cube.
What might be the possible cause of this.
thanks and regards
Murugesan
Hi Murgesan,
Please check at what level you are loading the key figure.
Are all the CVCs in the infocube existing in planning area ?
It will be useful to check for one specific CVC level, the value in infocube and value in planning area.
Please also check the period. Is the quantity getting added to next period ?
Regards
Datta