Error when generating settlement rule

Former Member
0 Kudos

Hello all

When i tried generating the settlement rule for internal project(investment project) i ended up with error message"No settings applicable to strategy Y2 found".Please anyone help me regarding this.Should we determine strategy for settlement rule in customizing?????

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

check the strategy rule setting in spro and assign to project profile.

regards,

Former Member
0 Kudos

Hello,

Strategy Y2 is maintained in project profile.In determine strategy in customizing should i assign "cost centre" for account assignment.In my system it is showing ''profitability segment'' maintained.

Former Member
0 Kudos

Account Assignmnet Category should be based on your business requirement. You can use the cost centre if that is what is needed but make sure in the settlement profile it is permissible to settle to a cost centre.