BAPI_PBSRVAPS_GETDETAIL - pick only 18 months

Former Member
0 Kudos

Hi Gurus

We have 'z' program where in Bapi 'BAPI_PBSRVAPS_GETDETAIL' is used to fetch data from SNP planning book to check available capacity of the the resources.

Now the problem is system calculate capacity for only 18 months taking data from LC, eventhough there is data in planning book for complete 24 months and planning area intialized for 24 months.

If someone has similar issue and it resolved ... please share with me.

Quick help is much appriciated

regards

V

Accepted Solutions (0)

Answers (1)

Answers (1)

pavan_verma2
Contributor
0 Kudos

Hi Kiran,

What is the range of days maintained in planning parameters of the resource.

Thanks

Pavan Verma

Former Member
0 Kudos

Hi Pavan

Thanks for reply

In resource planning parameter it is -30 and +730 days.

regards

Kiran