Handling resource downtime not respected

Former Member
0 Kudos

In location master in resources tab assigned handling resource in Resource Inbound field for which maintained downtime in resource master. But SNP heuristics planning creatied purchase requisition for down time period. where else setting required to avoidcreation of order during downtime

Accepted Solutions (1)

Accepted Solutions (1)

former_member492024
Active Participant
0 Kudos

Hello,

Is this happening when using heuristic?

If so, the Heuristic will ignore the down time, since Heuristics is infinite and never consider the down time in the capacity profile.

As example The note 929624 is to consider the factory calendar in the resource master data, but not the capacity profile.

SNP Heuristics don't support the down time functionality.

The best regards,

michel Bohn